Establishment of Processing Facility of Construction & Demolition waste generated from Zones 1 to 8 at Kodungaiyur site and disposal of rejects to the Dump Site of Greater Chennai Corporation (The Authority)

Project Name: 2

Establishment of Processing Facility of Construction & Demolition waste generated from Zones 9 to 15 at Perungudi site and disposal of rejects to the Dump Site of Greater Chennai Corporation (The Authority)

Project Name 1: Establishment of Processing Facility of Construction & Demolition waste generated from Zones 1 to 8 at Kodungaiyur site and disposal of rejects to the Dump Site of Greater Chennai Corporation (The Authority)
Project Name 2: Establishment of Processing Facility of Construction & Demolition waste generated from Zones 9 to 15 at Perungudi site and disposal of rejects to the Dump Site of Greater Chennai Corporation (The Authority)

Project description

Project Area: 1
15 acres

Project Area: 2
15 acres

Plant Capacity:
2 x 400 MT/ Day

Lifecycle Cost:
Rs.5731.60 million

SALIENT FEATURES

The generated C&D waste within the project area will be collected and transported to the Processing facility. The Waste that reached the facility will be processed in compliance with C&D waste management rules 2016 which includes washing of C&D waste, Crushing of Waste and converting the waste into different size fractions (GSB), making into products like M-Sand, Paver Blocks etc.